back home A2 Świecko - Konin | Every kilometer matters
Back

Works will be continued since 7th March – extension of the Poznań bypass

Road signs will be installed from 7th March 8 pm to 8th March 6 am between the Poznań Zachód and Poznań Luboń interchanges.

Works will be continued on the northern lane (Świecko direction), where fast lane will be taken along the lenght from 164km+800 to 164km+ 000 and from 161km+200 to 160km+200.

Passageways are planned to be build in Poznań Luboń and Poznań Komorniki interchange on weekend. Detailed information on:  Budowa przewiązek – start rozbudowy.

Schedule presented above can change, due to weather conditions.
Information about traffic flow from Konin to Świecko is available on: twitter.com/AutostradaWlkp and on Hotline number: 0 800 022 242.