Update. Next stage of pavement renovation of A2 on section Poznań – Września

The next stage of the works related to wearing course exchange on section Poznań-Września will be continuated (171km+600-193km+950). Temporary traffic system will be introduced on indicated sections of motorway.

Schedule of works:

• 11.10 section 176km+050 – 179km+050 of southern road (Warsaw direction) reintroduced for passage
• 9-17.10 closure of southern road (Warsaw direction), northern road-lanes drive on section 179km+250 – 181km+300
• 15-19.10 temporary traffic organization on southern road (Nagradowice Toll Plaza). Section 181km+300 – 182km+000
• 22.10 temporary traffic organization on northern road (Nagradowice Toll Plaza). Estimated time of work: 5 days

Schedule presented above can change, due to weather conditions.