Road resurfacing at the Poznań Komorniki junction
On 27 July 2026, Autostrada Wielkopolska SA will commence road resurfacing works at the Poznań Komorniki junction (159 km A2).…
Read more
home
A2 Świecko - Konin | Every kilometer matters
The next stage of the works related to wearing course exchange on section Poznań-Września will be continuated (171km+600-193km+950). Temporary traffic system will be introduced on indicated sections of motorway.
Schedule of works:
• 2-12.10 closure of southern road (Warsaw direction), northern road-lanes drive on section 176km+050 – 179km+050.
• 8.10 no possibility of entry to Rest or Service Area Krzyżowniki (including the petrol station).
• 8.10 section 171m+500 – 176km+050 (Poznań East interchange) of southern road (Warsaw direction) reintroduced for passage.
• 9-19.10 closure of southern road (Warsaw direction), northern road-lanes drive on section 179km+250 – 181km+300. Estimated time of work: 10 days.
Schedule presented above can change, due to weather conditions.
Information about traffic flow from Konin to Świecko is available on: twitter.com/AutostradaWlkp and on Hotline number: 0 800 022 242