Road resurfacing at the Poznań Komorniki junction
On 27 July 2026, Autostrada Wielkopolska SA will commence road resurfacing works at the Poznań Komorniki junction (159 km A2).…
Read more
home
A2 Świecko - Konin | Every kilometer matters
The next stage of the works related to wearing course exchange on section Poznań-Września will be continuated (171km+600-193km+950). Temporary traffic system will be introduced on indicated sections of motorway.
Schedule of works:
• 28.09 (4 pm) southern road (Warszawa direction) reintroduced for passage, closure of a part of rapid lane on northern road (Świecko direction). Section 176km+050 – 171km+500 (near Krzesiny Interchange)
• 29.09 – 8.10 closure of southern road (Warszawa direction), northern road-lanes drive on section 171km+500 – 176km+050 (between Krzesiny Interchange and Poznań East Interchange)
• 2.10 – 12.10 closure of southern road (Warszawa direction), northern road-lanes drive on section 176km+050 – 179km+050. Estimated time of work: 10 days
Schedule presented above can change, due to weather conditions.
Information about traffic flow from Konin to Świecko is available on: twitter.com/AutostradaWlkp and on Hotline number: 0 800 022 242