Road resurfacing at the Poznań Komorniki junction
On 27 July 2026, Autostrada Wielkopolska SA will commence road resurfacing works at the Poznań Komorniki junction (159 km A2).…
Read more
home
A2 Świecko - Konin | Every kilometer matters
The next stage of the works related to wearing course exchange on section Poznań-Września will be continuated (171km+600-193km+950). Temporary traffic system will be introduced on indicated sections of motorway.
Schedule of works:
• 27/28.06 section 205km+950 – 209km+480 of southern road reintroduced for passage
• 27/28.06 closure of northern road, southern road-lanes drive on section 190km+150- 193km+950. Estimated time of work: 10-12 working days
• 3/4.07 section 193km+950 – 196km+950 of northern road reintroduced for passage
3/4.07 closure of northern road, southern road-lanes drive on section 186km+900 – 190km+150. Closure of emergency exit (186km+895). Estimated time of work: 10-12 working days
• 6/7.07 section 190km+150 – 193km+950 of northern road reintroduced for passage
7/8.07 closure of northern road, southern road-lanes drive on section 181km+950 – 186km+900. Closure of emergency exit (186km+895). Estimated time of work: 10-12 working days
Schedule presented above can change, due to weather conditions.
Information about traffic flow from Konin to Świecko is available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00 a.m. and 8.00 p.m.)