Road resurfacing at the Poznań Komorniki junction
On 27 July 2026, Autostrada Wielkopolska SA will commence road resurfacing works at the Poznań Komorniki junction (159 km A2).…
Read more
home
A2 Świecko - Konin | Every kilometer matters
From May 14th the works related to wearing course exchange on section Poznań-Września start. Temporary traffic system will be introduced on indicated sections of motorway.
Schedule of works:
• 14-22.05 closure of northern road, southern road-lanes drive on section 209km+480 – 205km+950.
• 16-28.05 closure of northern road, southern road-lanes drive on section 205km+950 – 202km+350. Closure of emergency exit (203km+930), northern side
• 19.05 closure of slip road A on Słupca Interchange (208km) – no possibility of leaving the motorway to Września for those coming from Konin and closure of slip road D – the lack of access to the motorway in direction of Poznań. Closure of emergency exit (207km+930)
• 22.05 closure of northern road, southern road-lanes drive on section 202km+350 – 199km+850
Schedule presented above can change, due to weather conditions.
Information about traffic flow from Konin to Świecko is available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00 a.m. and 8.00 p.m.)