Pavement renovation of A2 on section Poznań – Września

From May 14th the works related to wearing course exchange on section Poznań-Września start. Temporary traffic system will be introduced on indicated sections of motorway.

Schedule of works:
• 14-22.05 closure of northern road, southern road-lanes drive on section 209km+480 – 205km+950.
• 16-28.05 closure of northern road, southern road-lanes drive on section 205km+950 – 202km+350. Closure of emergency exit (203km+930), northern side
• 19.05 closure of slip road A on Słupca Interchange (208km) – no possibility of leaving the motorway to Września for those coming from Konin and closure of slip road D – the lack of access to the motorway in direction of Poznań. Closure of emergency exit (207km+930)
• 22.05 closure of northern road, southern road-lanes drive on section 202km+350 – 199km+850

Schedule presented above can change, due to weather conditions.