Update. Next stage of pavement renovation of A2 on section Poznań – Września

The next stage of the works related to wearing course exchange on section Poznań-Września will be continuated (171km+600-193km+950). Temporary traffic system will be introduced on indicated sections of motorway.

Schedule of works:
• 27/28.06 section 205km+950 – 209km+480 of southern road reintroduced for passage
• 27/28.06 closure of northern road, southern road-lanes drive on section 190km+150- 193km+950. Estimated time of work: 10-12 working days
• 3/4.07 section 193km+950 – 196km+950 of northern road reintroduced for passage
3/4.07 closure of northern road, southern road-lanes drive on section 186km+900 – 190km+150. Closure of emergency exit (186km+895). Estimated time of work: 10-12 working days
• 6/7.07 section 190km+150 – 193km+950 of northern road reintroduced for passage
7/8.07 closure of northern road, southern road-lanes drive on section 181km+950 – 186km+900. Closure of emergency exit (186km+895). Estimated time of work: 10-12 working days

Schedule presented above can change, due to weather conditions.

Information about traffic flow from Konin to Świecko is available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00 a.m. and 8.00 p.m.)