Early completion of stage I of the Poznań Bypass works. New temporary traffic organization to be launched as of 24 April

Stage I of the construction project at the Poznań Bypass has been completed.  The third lane was built in the section between Poznań Komorniki and Poznań Luboń interchanges and guard rails were installed. Now, the works will be shifted to the other carriageway.  On Easter Monday,  22 April, since 12:00 a.m. the road construction teams will begin preparations to change the temporary traffic organization.  The new scheme will be in place already on Wednesday 24 April, since the early hours. 

The first stage of the project was completed at an express pace of works and comprises 6 km of the third lane, with pavement matching the existing vertical alignment on the southern carriageway (Warsaw- bound) between the interchanges of Poznań Komorniki and Poznań Luboń.   Starting 24 April, the contractor – A2 Route/Strabag JV will launch the new traffic organization scheme.  All traffic will be diverted to the southern carriageway where 4 lanes will be available, separated by moveable barriers, two lanes in each direction. Only the slow lane in both directions will be available for heavy vehicles. The northern carriageway (Świecko-bound) will be fully occupied as a job site with third lane works carried out there.

The temporary organization scheme implemented last month in the section Poznań West – Poznań Komorniki will remain unchanged, i.e. traffic on each carriageway has two lanes available in each direction with the emergency lane fenced as job site.  That scheme will continue for the next weeks until the first half of June. 

As the works progress, the slip road from Poznań and Luboń to Świecko will be closed. 

Traffic options are illustrated in the picture below:

5bcb4cf59cf1fb6798be73babb61b0a68c3879ba

We are happy to see the first, very important stage of the Bypass works completed as scheduled, at a very express pace.  The 12-hour working system involving almost 200 people using ca. 80 machines and vehicles coupled with round the clock work during the last weekends contributed to the completion of the third lane which matches the existing vertical alignment in the 6 km long section of the motorway,  says Zofia Kwiatkowska, the spokesperson for Autostrada Wielkopolska S.A. -The weather was fine so far, and it’s one of the major factors of successful performance.  We are also very happy to see that the temporary traffic organization scheme implemented some weeks ago has been working perfectly well, despite huge traffic volume reaching 60 thousand vehicles a day.  No standstills occurred, and traffic was as smooth as it was possible, adds Kwiatkowska. 

In the weeks to come the contractor will, among other works, dismantle the median and shoulder guard rails and rehabilitate the bridge structures.

A2 Motorway is the major international link between eastern and western Poland.  Around 65 thousand vehicles drive each day on the Poznań Bypass, which adds up to ca. 23 million drivers a year.  The cost of the works in the 16 km stretch of the Bypass is PLN 200 million and is fully funded by the employer, Autostrada Wielkopolska S.A..  It is the first time that works involving widening of a motorway are performed under traffic, without closing the road, on the contrary, maintaining two lanes in each direction. 

Pictures of the Bypass works: download here