Road resurfacing at the Poznań Komorniki junction
On 27 July 2026, Autostrada Wielkopolska SA will commence road resurfacing works at the Poznań Komorniki junction (159 km A2).…
Read more
home
A2 Świecko - Konin | Every kilometer matters
The next stage of the works related to wearing course exchange on section Poznań-Września will be continuated (171km+600-193km+950). Temporary traffic system will be introduced on indicated sections of motorway.
Schedule of works:
• 5.09 section 181m+300 – 179km+250 (Poznań East interchange) of northern road (Świecko direction) reintroduced for passage
• 10.09 – 18.09 closure of northern road (Świecko direction), southern road-lanes drive on section 179km+250 – 176km+050. (Poznań East interchange). Estimated working time: 8 days. (Possibility of entry and exit on the Poznań East interchange. Joining traffic on the motorway for those traveling from Gniezno towards Poznań by the S5 road without the STOP sign.)
• 13.09 – 21.09 closure of northern road (Świecko direction), southern road-lanes drive on section 176km+050 – 171km+500. Between 13.09 and 18.09 closure both section: 179km+250 – 171km+500 (between Poznań Wschód and Poznań Krzesiny interchanges)