back home A2 Świecko - Konin | Every kilometer matters
Back

Update. Next stage of pavement renovation of A2 on section Poznań – Września

The next stage of the works related to wearing course exchange on section Poznań-Września will be continuated (171km+600-193km+950). Temporary traffic system will be introduced on indicated sections of motorway.

Schedule of works:
• 4.07 – 18.07 closure of northern road, southern road-lanes drive on section 190km+150 – 186km+900
• 12.07 section 193km+950 – 190km+150 of northern road reintroduced for passage
• 12.07 – 24.07 closure of northern road, southern road-lanes drive on section 186km+900 – 181km+950
• 26.07 closure of southern road, northern road-lanes drive on section 181km+950 – 186km+900. Estimated time of work: 10-12 working days

Schedule presented above can change, due to weather conditions.

Information about traffic flow from Konin to Świecko is available on: twitter.com/AutostradaWlkp and on Hotline number: 0 800 022 242