Update. Next stage of pavement renovation of A2 on section Poznań – Września

The next stage of the works related to wearing course exchange on section Poznań-Września will be continuated (171km+600-193km+950). Temporary traffic system will be introduced on indicated sections of motorway.

Schedule of works:
• 4.07 closure of northern road, southern road-lanes drive on section 186km+900 – 190km+150. Estimated time of work: 10-12 working days
• 12.07 section 190km+150 – 193km+950 of northern road reintroduced for passage
• 13.07 closure of northern road, southern road-lanes drive on section 182km+000 – 186km+900. Estimated time of work: 10-12 working days
• 16.07 section 186km+900 – 190km+150 northern road reintroduced for passage
• 18.07 closure of southern road, northern road-lanes drive on section 182km+000 – 186km+900. Estimated time of work: 10-12 working days

Schedule presented above can change, due to weather conditions.