Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway.

Schedule of works:

  • 22.09 Closed of northern road (direction Świecko) on section 224km+900-232km+300, two-way passage on southern roadway (direction Warszawa).
  • Emergency entrance on 229km+173 is closed for passage for the time of works. Closed slip road D on Słupca I/C with a passage from A2 in direction of Świecko to DW466 in direction of Słupca. Passage to Słupca and Pyzdry lead by detour:

– Direction Słupca – A2 to Września I/C, then DK92 through Września till Słupca
– Direction Pyzdry – A2 to Września I/C, then from DK92 to DW442 till Pyzdry

  • Opening of slip road D: 5/6.10.2017. due to works mentioned above, closure of CSA Skarboszewo (226km+500) and service gate on CSA.
  • 2/3.10 Closure of northern road (direction Świecko) on section 220km+900-224km+900, two way passage on southern roadway (direction Warszawa). Emergency entrance on 221km+628 is closed for passage for the time of works.
  • 11/12.10 Section 224km+900-232km+300 of norhern road (direction Świecko) reintroduced for passage.
  • 11/12.10 Closure of northern road (direction Świecko) on section 216km+950-220km+900, two way passage on southern roadway (direction Warszawa).
  • 14/15.10 Section 220km+900-224km+900 of norhern road (direction Świecko) reintroduced for passage.
  • 16/17.10 Closure of northern road (direction Świecko) on section 209km+500-216km+950, two way passage on southern roadway (direction Warszawa). Emergency entrance on 216km+490 is closed for passage for the time of works:

– One-day closure of exit road to Sołeczno CSA – exact date soon.

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.
Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. Works will last till October 2017. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)