Pavement renovation of A2 on section Września-Konin

Continuation of pavement renovation of main road A2 motorway, section Września-Konin. There will be temporal traffic system on pointed sections of motorway.

Schedule of works:

  • 5.09 Closure of northern road (direction Świecko) on section 240km+100-244km+200, two-way passage on southern roadway (direction Warszawa).
  • 7/8.09 Closure of slip road A with a passage on Sługocin Interchange from DW467 to A2 in direction of Poznań
  • 9/10.09 Section 244km+200-248km+100 of northern road reintroduced for passage.
  • 9/10.09 Closure of northern road (direction Świecko) on section 236km+200-240km+100, two-way passage on southern roadway (direction Warszawa). Emergency entrance on 237km+917 is closed for passage for the time of works.
  • 12/13.09 Section 240km+100-244km+200of northern road reintroduced for passage.
  • 12/13.09 Closure of northern road (direction Świecko) on section 232km+300-236km+200, two-way passage on southern roadway (direction Warszawa).

Schedules presented above can change, due to weather conditions and current traffic intensity within section of works.

Works will be conducted according to heavy maintenance plan, that assumes (same as in case of public motorways) pavement renovation after 10 years of using. Works will last till October 2017. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Poznań, General Directorate for National Roads and Motorways, Autostrada Wielkopolska Inc. and Autostrada Eksploatacja Inc.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)