back home A2 Świecko - Konin | Every kilometer matters
Back

Renovation works on trunk road DK2, DK29 and slip roads on Świecko Interchange

On Friday, 1st of September begun another stage of renovation works within Świecko Interchange (3km of motorway). Works will be organized on trunk road DK29, DK2 and slip roads C, C1, D, D1, E of Świecko Interchange. The renovation of mentioned objects will last till 8th of September.

Scheduled working schemes:

  • 1.09-8.09 Continuation of works on DK29 and slip roads C, C1, D, D1, E – works connected to reconstruction of horizontal marking, roadside cambering, regulation of gutters and resilient bars on slip roads.
  • 1.09-8.09 works on left roadway of DK2 (direction Świecko) – renovation of left and half of right lane, section 2+800km – 3+375km

Schemes of works can be changed depending on the weather conditions and current traffic intensity within the Interchange.

Works are conducted within Świecko Interchange. The executor of the works is Strabag LLC (person to contact with: Marcin Szczepański, tel. +48 695 020 857).

The temporal traffic system was agreed with Provincial Police Headquarters in Gorzów Wlkp., General Directorate for National Roads and Motorways in Zielona Góra, Autostradą Wielkopolską Inc, Autostradą Eksploatacja Inc, National Road District in Słubice. German side was informed about renovation of Świecko Interchange by executor of works.

Information about passage condition from Konin to Świecko are available on: twitter.com/AutostradaWlkp and on Hotline number +48 504 422 022 (everyday between 8.00a.m. and 8.00 p.m.)